- Registered

This interface provides information on the last 15 CDM project activities that have been registered by the CDM Executive Board. CDM project activities registered earlier are accessible through the Project Search interface.

Registered Title Host Parties Other Parties Methodology * Reductions ** Ref
31 Dec 20 10 MW Solar Power Project by Krishna Wind Farm Developers Pvt. Ltd. India AMS-I.D. ver. 18
18123
10634
31 Dec 20 Bundled Solar Power Project by Emami Power Limited India AMS-I.D. ver. 18
21633
10568
23 Dec 20 Hasang Hydro Electric Power Plant Indonesia ACM0002 ver. 20
216320
10632
22 Dec 20 Ras Ghareb Wind Energy Project Egypt ACM0002 ver. 20
730788
10625
21 Dec 20 Wind Power Project by Mangalam Fashions Limited & Group in Andhra Pradesh India AMS-I.D. ver. 18
14980
10636
14 Dec 20 Solar and Wind Project by Agrawal Renewable Energy Pvt. Ltd India AMS-I.D. ver. 18
14103
10626
21 Oct 20 Expansion San Pedro Wind Farm Chile United Kingdom of Great Britain and Northern Ireland ACM0002 ver. 20
119235
10611
07 Oct 20 Renewable Energy Power project by DDWL India ACM0002 ver. 20
59407
10602
24 Sep 20 Solar Project by Parampujya Solar Energy Pvt. Ltd. India ACM0002 ver. 20
111603
10603
11 Sep 20 250 MW Solar Power Plant in Pavagada Solar Park in Karnataka India ACM0002 ver. 20
467318
10573
27 Aug 20 50 MW (DCR) Nalgonda Solar PV Power Project by Parampujya Solar Energy at Telangana India ACM0002 ver. 20
103900
10593
27 Aug 20 50 MW Mahoba Solar PV Power Project by M/s Prayatna Developers Pvt. Ltd. at Mahoba, UP India ACM0002 ver. 20
94769
10594
27 Aug 20 50 MW Kurnool Solar PV Power Project by M/s Prayatna Developers Pvt. Ltd. at Gani, Kurnool, AP. India ACM0002 ver. 20
90081
10592
04 Aug 20 216 MWac Adani Green Energy (Tamilnadu) Solar Power Project India ACM0002 ver. 20
332919
10583
04 Aug 20 72 MWac Ramnad Solar Power Project India ACM0002 ver. 20
110973
10582

* AM - Large scale, ACM - Consolidated Methodologies, AMS - Small scale
** Estimated emission reductions in metric tonnes of CO2 equivalent per annum (as stated by the project participants)

Background:
In accordance with the modalities and procedures for a CDM   Decision 3/CMP.1 (735 KB) :
"41. The registration by the Executive Board shall be deemed final eight weeks after the date of receipt by the Executive Board of the request for registration, unless a Party involved in the project activity or at least three members of the Executive Board request a review of the proposed CDM project activity. The review by the Executive Board shall be made in accordance with the following provisions

  • (a) It shall be related to issues associated with the validation requirements;
  • (b) It shall be finalized no later than at the second meeting following the request for review, with the decision and the reasons for it being communicated to the project participants and the public."