Grid connected bundled wind projects in Gujarat and Tamil Nadu
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 17
Standardised Baselines N/A
Estimated annual reductions* 6,748
Start date of first crediting period. 01 Apr 12
Length of first crediting period. 7 years
DOE/AE LRQA Ltd
Period for comments 05 Nov 11 - 04 Dec 11
PP(s) for which DOE have a contractual obligation M/s GMR Power Infra Limited
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (974 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
DOE to check how accelerated depreciation benefits are accounted for. 
In case GBI is availed cant the PP also avail accelerated depreciation benefits?
Is the PP selling electricity to State Electricity Board or to third party? How is the tariff rate reasonable?
Is the PP claiming or will claim any REC benefits?
Does the PP have any RPO obligation and is the project being installed for meeting RPO obligations?
Submitted by: Babloo


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs