21:50 09 Mar 22
Project:
0707 India-FaL-G Brick and Blocks Project No.1
- Request for post-registration changes
| Project | 0707 India-FaL-G Brick and Blocks Project No.1 |
|---|---|
| PRC ref | PRC-0707-001 |
| Process track | Prior approval |
| DOE | DNV |
|
Methodology(ies) and/or Standardized Baseline(s)
applied at the post-registration changes |
|
| Methodology(ies) list | |
| Standardized baseline(s) list | |
| DOE conducted validation of the changes | When performing a verification for the project activity or PoA stated above (See footnote 1 below) |
| Type of submission |
Permanent changes from the monitoring plan or the monitoring methodology
Changes to the project or programme design
|
| Applicable crediting period | 01 Apr 04 - 31 Mar 14 |
| Assessment opinion |
Assessment opinion (213 KB)
|
| Revised PDD |
Revised PDD (1230 KB)
Revised PDD - track changes (1361 KB)
|
| Supplementary documents | |
| Signed form |
Signed form (156 KB)
|
| DOE clarification |
|
| VVS version | VVS 2.0 |
| Current status | 07 Oct 13 -
Approved
Effective approval date: 07 Oct 13
|
| Historic statuses |
30 Jul 13 -
Published 19 Aug 13 - Awaiting DOE clarifications 02 Sep 13 - DOE clarifications received 02 Sep 13 - Summary note being prepared 16 Sep 13 - Awaiting EB decision |

Assessment opinion
Join the Climate Neutral Now initiative:
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: