2.10 MW Wind Power Project by M/s Chhotabhai Jethabhai Patel & Co. (CJP) at Belwa Ranaji Village, Shergarh Taluka, Jodhpur District, Rajasthan, India.
[]
Host party(ies) India
Methodology(ies) AMS-I.D. ver. 15
Standardised Baselines N/A
Estimated annual reductions* 3,462
Start date of first crediting period. 31 Oct 10
Length of first crediting period. 10 years
DOE/AE RINA Services S.p.A.
Period for comments 15 May 10 - 13 Jun 10
PP(s) for which DOE have a contractual obligation M/s Chhotabhai Jethabhai Patel & Co. (CJP)
The operational/applicant entity working on this project has decided to make the Project Design Document (PDD) publicly available directly on the UNFCCC CDM website.
PDD PDD (624 KB)
Local stakeholder consultation report: N/A
Impact assessment summary: N/A
Submission of comments to the DOE/AE Compilation of submitted inputs:
The proponent says the project is not viable without CDM benefit but then again with a lower return even after considering CDM benefit the proponent is going ahead with the project. the understanding seems strange as why would a investor invest if he is not getting the return he wants by investing. cHarity?

DOE please check
Submitted by: Arnab deb


The comment period is over.
* Emission reductions in metric tonnes of CO2 equivalent per annum that are based on the estimates provided by the project participants in unvalidated PDDs