3827 Bundled Hadong-Busan photovoltaic Power Project of The Korea Southern Power Corporation (1MW Hadong Photovoltaic Power + 0.39MW Busan Photovoltaic Power, Bundling Project)
- Issuance Request
| Project | 3827: Bundled Hadong-Busan photovoltaic Power Project of The Korea Southern Power Corporation (1MW Hadong Photovoltaic Power + 0.39MW Busan Photovoltaic Power, Bundling Project) |
|---|---|
| ISSUANCE STATUS | Issued (on 20 Mar 18) completeness check: complete | info & rep check: concluded |
| Monitoring period | 18 Dec 10 - 31 Dec 16 |
| Monitoring report |
Monitoring report (541 KB)
|
| Submission of comments to the DOE | |
| Requests for post-registration changes containing applicable deviations | PRC-3827-001 - Approved |
| Requests for post-registration changes submitted with the issuance request | PRC-3827-001 |
| Request for issuance |
Signed form (458 KB)
|
| Amount of CERs |
CERs issued up to 31 December 2012:
1,807
CERs issued from 01 Jan 2013 until 31 December 2020: 3,328 Total amount of CERs: 5,135
Serial Range:
Block start: KR-5-165852107-1-1-0-3827
Block end: KR-5-165853913-1-1-0-3827
Serial Range: Block start: KR-5-165853914-2-2-0-3827 Block end: KR-5-165857241-2-2-0-3827 |
| Verification and certification reports |
VVS/VVM version:
VVS-PA 1.0
Certification report (797 KB)
Verification report (797 KB)
|
| Additional documents |
Monitoring report_ver.02 (580 KB)
ER Spreadsheet (Hadong-Busan photovoltaic Power Project_ver.02.xlsx (174 KB)
|

Monitoring report
ER Spreadsheet (Hadong-Busan photovoltaic Power Project_ver.02.xlsx
Join the Climate Neutral Now initiative:
Offset now: visit the United Nations Carbon Offset Platform
Connect with us: