Project:
1253 Baragran Hydro Electric Project, 3.0 MW (being expanded to 4.9 MW)
- Issuance Request
| Project | 1253: Baragran Hydro Electric Project, 3.0 MW (being expanded to 4.9 MW) |
|---|---|
| ISSUANCE STATUS | Issued (on 15 Dec 21) completeness check: complete | info & rep check: concluded |
| Monitoring period | 01 Jan 20 - 31 Dec 20 |
| Monitoring report |
Monitoring report (652 KB)
|
| Request for issuance |
Signed form (64 KB)
|
| Amount of CERs |
CERs issued from 01 Jan 2013 until 31 December 2020:
27,238
Serial Range:
Block start: IN-5-274298446-2-2-0-1253
Block end: IN-5-274325683-2-2-0-1253
|
| Verification and certification reports |
VVS/VVM version:
VVS-PA 2.0
Certification report (349 KB)
Verification report (349 KB)
|
| Additional documents |
Untitled (uploaded 14 Sep 21 15:56:15) (444 KB)
1253 ER Calculation Sheet 25-08-21 v2.xlsx (39 KB)
|

Monitoring report
1253 ER Calculation Sheet 25-08-21 v2.xlsx